![]() |
Telelogic SYNERGY (steve huntington) | ![]() |
Topic Title: Release predecessor and reconfigure process Topic Summary: Created On: 24-Aug-2004 16:45 Status: Read Only |
Linear : Threading : Single : Branch |
![]() |
![]()
|
![]() Answer: Hello, Is it possible to define a priority between releases, that could be used in reconfigure process. Example : 2 releases "V1" (for V1 maintenance) and "V2" (for next application version development). object "O" has 1 version in each release : - "OV1" created on 2003/01/01 in release "V1" - "OV2" created on 2003/12/31 in release "V2", successor of "OV1" In release "V1", I create another successor "OV1bis" to "OV1" on 2004/01/01. "OV1bis" and "OV2" are parallel versions in different releases. The reconfigure properties of my V2 project are : - a "V1" baseline - all completed tasks in release "V1" - all completed tasks in release "V2" After reconfigure, I get "OV1bis" because it is newer than "OV2". Is it possible to define that "V2" release is successor of "V1", so that if there are candidates in "V2", "V1" candidates are eliminated of reconfigure process, so I get "OV2" until "OV1bis" modifications are merged in "V2" release ? | |
![]() |
|
Hello,
Is it possible to define a priority between releases, that could be used in reconfigure process. Example : 2 releases "V1" (for V1 maintenance) and "V2" (for next application version development). object "O" has 1 version in each release : - "OV1" created on 2003/01/01 in release "V1" - "OV2" created on 2003/12/31 in release "V2", successor of "OV1" In release "V1", I create another successor "OV1bis" to "OV1" on 2004/01/01. "OV1bis" and "OV2" are parallel versions in different releases. The reconfigure properties of my V2 project are : - a "V1" baseline - all completed tasks in release "V1" - all completed tasks in release "V2" After reconfigure, I get "OV1bis" because it is newer than "OV2". Is it possible to define that "V2" release is successor of "V1", so that if there are candidates in "V2", "V1" candidates are eliminated of reconfigure process, so I get "OV2" until "OV1bis" modifications are merged in "V2" release ? |
|
![]() |
|
![]() |
|
Hi Stephane,
what You are looking for is perhaps task based CM with release scoring. Take a look at TB-169 in the knowledgebase. This method sometimes is a bit tricky and its not recommended by Telelogic, but I worked that way once and had no special problems. IMHO its a just bit problematic because of the break with pure task based concept. Anyway the point is that the system does, what You want ![]() Regards, Mert |
|
![]() |
Telelogic SYNERGY
» SYNERGY/CM
»
Release predecessor and reconfigure process
|
![]() |
FuseTalk Standard Edition v3.2 - © 1999-2009 FuseTalk Inc. All rights reserved.