![]() |
Telelogic SYNERGY (steve huntington) | ![]() |
Topic Title: Error on checking in default task operation Topic Summary: Created On: 25-Oct-2006 20:23 Status: Read Only |
Linear : Threading : Single : Branch |
![]() |
![]()
|
![]() Answer: Thanks for answering my question ... I do not understand what is the operation on which the wrong association is beeing done ...: I´m new through CM Synergy and I work into software integration processes ... At this time I instruct all developers to let project level checked out, and when a work is done they are used to checkin all objects and, at the end, they checkin the default task (without checking in the project) ... The developer continue on working after by creating a new task and, if needed, checking out required objects (and sometimes there´s a need to touch on same objects they just delivered on which I didn´t integrated yet ...) Is it usual for you guys? (... I do ask this because my mistake must happen on the way we approach related processes). thanks for your support. | |
![]() |
|
Hello everybody. Warning: This task cannot be completed because your role does not permit check in of a project. You must either have the component_developer role, or be in the ccm_admin or build_mgr role to check in a project. Check In Task IcoRR10#472 -- failed. |
|
![]() |
|
![]() |
|
You would appear to have associated a non-static project with the task.
If this was not intended, then remove the project. If it was intended, then you will need to have one of the privileges mentioned to check in the project. I can think of very few circumstances where it is intended to associate a non-static project with a development task. |
|
![]() |
|
![]() |
|
Thanks for answering my question ...
I do not understand what is the operation on which the wrong association is beeing done ...: I´m new through CM Synergy and I work into software integration processes ...
At this time I instruct all developers to let project level checked out, and when a work is done they are used to checkin all objects and, at the end, they checkin the default task (without checking in the project) ...
The developer continue on working after by creating a new task and, if needed, checking out required objects (and sometimes there´s a need to touch on same objects they just delivered on which I didn´t integrated yet ...)
Is it usual for you guys? (... I do ask this because my mistake must happen on the way we approach related processes).
thanks for your support.
|
|
![]() |
Telelogic SYNERGY
» SYNERGY/CM
»
Error on checking in default task operation
|
![]() |
FuseTalk Standard Edition v3.2 - © 1999-2009 FuseTalk Inc. All rights reserved.