Projects |
Total Planned Effort |
Integer |
PlannedEffort |
Planned Effort |
The planned effort in the CLM system is
shown as a progress bar in the iteration plan view in the Eclipse
client. In the web client, the planned effort is in the iteration
plan list view. |
Projects |
Total Actual Effort |
Integer |
ActualWork |
Actual Effort |
The actual effort in the CLM system is shown
as a progress bar in the iteration plan view in the Eclipse client.
In the web client, the actual effort is in the iteration plan list
view. |
Projects |
Planned Start Date |
Date |
PlannedStart |
Planned Start |
The planned start date is in the iteration
plan list view in the CLM system. |
Projects |
Planned End Date |
Date |
PlannedFinish |
Planned Finish |
The planned end date is in the iteration
plan lists view in the CLM system. |
Projects |
Last Snapshot Date |
Date |
SnapshotDate |
Snapshot creation date |
Before an update from the CLM system can
be done in Rational Focal Point,
you must take a snapshot in the CLM system. The date of the snapshot
is shown in Rational Focal Point after
the update. |
Projects |
Completeness (%) |
Integer |
PercentComplete |
Percent Complete |
The progress of all the business needs are
rolled up and displayed as the project completeness in the CLM system.
For example, 34% or 78%. |
Business Needs |
Planned Effort |
Integer |
PlannedEffort |
Estimate / Correction |
The estimate in the CLM system is shown
as the planned effort in Rational Focal Point.
If a correction is entered, the estimate is overridden. |
Business Needs |
Actual Effort |
Integer |
ActualWork |
Time Spent |
The time spent in the CLM system is shown
as the actual effort in Rational Focal Point. |
Business Needs |
Planned Start Date |
Date |
PlannedStart |
Planned Start |
The planned start date has information from
the work item timeline in the Gantt view (plan details) in the CLM
system. |
Business Needs |
Actual Start Date |
Date |
ActualStart |
Actual Start |
The actual start date has information from
the work item timeline in the Gantt view (plan details) in the CLM
system. |
Business Needs |
Planned End Date |
Date |
PlannedFinish |
Planned Finish |
The planned end date is populated with information
from the work item timeline in the Gantt view (plan details) in the
CLM system. |
Business Needs |
Actual End Date |
Date |
ActualFinish |
Actual Finish |
The actual end date is populated with information
from the work item timeline in the Gantt view (plan details) in the
CLM system. |
Business Needs |
Last Snapshot Date |
Date |
SnapshotDate |
Snapshot creation date |
The
last snapshot date for a business need will be the same date as for
the project that it is related to. |
Business Needs |
Completeness (%) |
Integer |
PercentComplete |
Percent Complete |
The progress of all the children work items
are rolled up and is displayed as percentage completeness in the CLM
system. For example, 34% or 78%. |
Business Needs |
Work Items |
CALM Link |
WorkItem |
- |
The work items attribute in Rational Focal Point links
to the work item in the CLM system. |
Business Needs |
Work Item State |
Text |
State |
Status |
The state of the work item in the CLM system. |