As a project or program manager, or even as a team member,
you will need to review the progress on the individual project activities,
and the overall project. You can use the percent effort complete (%EC),
percent complete (%C), and percent duration complete (%DC) information
in the Schedule Gantt viewlet to monitor and track project progress.
Before you begin
Use the Schedule Gantt viewlet to perform
this task. In the navigation bar, click Work,
and click the Schedule tab.
About this task
For information on the %EC, %C, and %DC fields, see
Percent completion values for project tracking
Procedure
Expand the project in the WBS tree. You can view the status
of the project and the individual project elements. - For an effort-based project, in the Schedule grid, view the
values of the %EC (percent effort complete) and %C (percent complete)
fields for the project elements. In the Gantt chart view, see the
progress bars in blue that represents the %EC value for an element,
for example,
. Hover the
mouse over the bar to view the detailed progress information
. The element
name, plan dates, and % EC are displayed in the tooltip.
- For a duration-based project, in the Schedule grid, view the
value of the %DC (percent duration complete) and the %C (percent complete)
fields. In the Gantt chart, for the project elements, see the progress
bar that represents the %DC value.
Note: %C values are blank unless a team member or project manager
enters these in the timesheet.