Tracking project progress

As a project or program manager, or even as a team member, you will need to review the progress on the individual project activities, and the overall project. You can use the percent effort complete (%EC), percent complete (%C), and percent duration complete (%DC) information in the Schedule Gantt viewlet to monitor and track project progress.

Before you begin

Use the Schedule Gantt viewlet to perform this task. In the navigation bar, click Work, and click the Schedule tab.

About this task

For information on the %EC, %C, and %DC fields, see Percent completion values for project tracking

Procedure

Expand the project in the WBS tree. You can view the status of the project and the individual project elements.
Note: %C values are blank unless a team member or project manager enters these in the timesheet.

Feedback