Rebasing Work Areas

At appropriate times, the project manager creates baselines in the project integration stream, incorporating development changes that have been delivered. After the baseline has been tested and recommended by the administrator, rebase your development stream to keep your development work area current with new baselines.

For information about undoing a rebase operation, see Rational® ClearCase® Help.